On most industrial projects in Mexico the building is not what determines the production start date. The electrical connection is — and it runs on a calendar that no contractor controls and no amount of site acceleration can compress.
Why this is the critical path, and why it surprises people
Construction is a process you can resource: more crews, longer shifts, parallel fronts. An electrical service request is an administrative and engineering process with queues — a feasibility study, a technical review, a budget, possibly physical works on the utility side, then energisation.
You cannot buy your way through it the way you can buy your way through a slow concrete pour. The only real lever is starting it earlier.
BOX:The failure mode is specific and common: the building is finished, equipment is installed, and the plant cannot be commissioned because the service is not energised. Everything that was accelerated on site is wasted, and the carrying cost continues.
The sequence
The exact naming and steps vary by region and by service class, but the structure is consistent:
| 1 · Load study | An engineering calculation of demand: connected load, demand factor, power factor, growth allowance. This is yours to produce and it determines everything downstream. |
| 2 · Application | Submitted with the load study and site documentation. The service class (low, medium or high voltage) follows from the demand. |
| 3 · Feasibility | The utility assesses whether capacity exists at that point of the network. The answer may be yes, yes-with-works, or not at this location — and the third answer is the one you want before buying land. |
| 4 · Budget and agreement | Costs and obligations are defined, including any works required to reach your site. |
| 5 · Works | On the utility side, on your side, or both. This is where timelines diverge most between projects. |
| 6 · Metering and energisation | Inspection, metering installation, contract activation. |
⚠️ Duration varies substantially by region, by service class and by whether network reinforcement is required. Anyone quoting you a single number without knowing your load and your location is guessing. Get the answer from a current application at your actual site — it is the only reliable figure.
Service class is a design decision, not a formality
| Service class | Typical situation | What it changes for you |
|---|---|---|
| Low voltage | Small workshops, offices, light assembly | Simplest connection; little infrastructure on your side |
| Medium voltage | Most industrial plants | You build and own a substation: transformer, switchgear, protection, metering |
| High voltage | Large or energy-intensive plants | Substantially more infrastructure and engineering on your side; longer lead times on major equipment |
Crossing a threshold between classes changes the equipment you buy, the space you must reserve for it, and the lead time of that equipment. It should be known before the plant layout is frozen, because the substation needs a location, access for a transformer, and clearances.
Sizing the request: both errors are expensive
There are two ways to get the load study wrong, and they fail differently:
- Under-request — you get a service that works on day one and constrains you the moment a second line is added. Increasing capacity later means re-entering the same process from near the beginning, with the plant already operating.
- Over-request — you pay for infrastructure and, depending on tariff structure, for contracted demand you do not use. Oversizing is not a free safety margin.
The practical approach is to size for a defined future state rather than an imagined one: current process load, plus the specific expansion you can name, plus a normal engineering allowance — not 'double it to be safe'.
Two inputs people forget: HVAC for controlled environments is a large and continuous load, and compressed air is usually one of the biggest single consumers in a plant.
When you have to build the line yourself
If your site is not already served at the required class, the works to reach it may fall to you — medium-voltage line extension, poles or underground route, easements across third-party land, and a substation at your end.
This is one of the clearest differences between an industrial park and standalone land:
- In a park — distribution usually reaches the lot line, and the question is capacity available to your lot rather than whether a line exists.
- Standalone land — the line may need to be built, which adds engineering, materials, possibly land rights, and a construction window that is outside your control.
Ask it as one question: what exactly do I have to build, and who approves it?
Hedges, and when they are worth it
| Standby generation | Protects production against interruption. Normal for processes where a stoppage damages product or restart is slow. It is not a substitute for service — it does not shorten the connection process. |
| Self-supply / on-site generation | Solar on an industrial roof is common and can reduce consumption cost. It changes the economics, not the connection timeline, and it has its own permitting path. |
| Phased energisation | Where feasible, commission part of the plant at a lower service while the full connection proceeds. Worth asking about early — it is rarely offered unless you ask. |
What to ask before committing to a site
- What service class does my demand require, and is that class available at this point of the network?
- How much uncommitted capacity exists, and what does reaching my lot require?
- What works would be on my side, and do they need land rights from third parties?
- What is the current realistic duration — for a project of my class, at this location, right now?
- Can any part of it be phased?
A park or landlord that answers these in writing with a date is giving you something you can plan against. One that points at a brochure figure is not.
How we handle it
We treat the electrical connection as a separate line in the programme, not as a subtask of construction — because it does not behave like construction and it usually controls the date.
In preconstruction that means: producing the load study early, establishing available capacity at the specific site before the land commitment, identifying which works fall on the owner's side, and reserving substation location and transformer access in the layout from the first drawing rather than fitting it in later.
What we do not do: we are not the utility and do not control its timeline. What we can do is make sure the request is correct, complete and filed in the first weeks — which is where essentially all of the available compression lives.
