The fastest way into US production is usually a lease on a building that already exists. The market is full of new speculative warehouses, and on a broker's flyer they look ready. They are ready, for pallets. This is what the shell does not have, and what to check before the lease is signed rather than after.
A warehouse and a factory are different occupancies
A speculative building is permitted as a shell or as Group S-1 storage. Manufacturing is normally Group F-1, and becomes a high-hazard Group H occupancy if hazardous materials exceed the code's quantity limits. Moving from one to another is a change of occupancy: a new permit, a full code review and a new certificate of occupancy before production starts.
The number that surprises tenants is the occupant load. The building code counts a warehouse at one person per 500 square feet and an industrial area at one per 100. The same floor area is treated as holding five times as many people, and exits, egress width and travel distance are checked against that figure. Restrooms, break rooms and accessible routes follow the real headcount, and a shell built for a dozen warehouse staff has almost none of them.
In Texas, a commercial project of $50,000 or more is also registered with the state for accessibility review, on its own clock. See industrial construction in Texas.
Power: the shell has service for lights and dock doors
A warehouse electrical service is sized for lighting, dock equipment and a small office. A production line can need several times that, and the upgrade runs through the utility: a new or larger transformer, new service conductors and new switchgear. Those are the longest-lead items in most fit-outs, and they are outside the contractor's control.
- Ask the utility what capacity is available at that address before the letter of intent. The answer varies building by building within the same park.
- Confirm the service voltage. Most US industrial buildings are 480Y/277 V three-phase; some smaller ones are 208Y/120 V, which is poorly suited to industrial equipment and usually means a new service.
- Agree in the lease who owns the upgraded service at the end of the term.
There is a second electrical issue that imported lines meet at start-up. Every industrial control panel has a short-circuit current rating, and it must be at least equal to the fault current available where the machine connects. Panels built without that engineering often carry a rating of only 5 kA, while the bus near a large transformer can deliver several times more. The inspector will not allow the machine to be energized until the mismatch is engineered out. Collect the ratings from the machine builders while the equipment is still in the factory.
The slab was designed for racks, not machines
A speculative warehouse slab is designed for rack posts and lift trucks. It is generally unreinforced or lightly reinforced, and it has no provision for dynamic loads.
- Presses, injection molding machines, large machining centers and anything with vibration need isolated foundations. That means saw-cutting the slab, excavating inside a finished building, and pouring a block the landlord must approve.
- Pits, trenches and floor drains for process utilities, and underslab plumbing for new restrooms, mean more cutting.
- Ask whether the slab is post-tensioned. Cutting a post-tensioned slab without locating the tendons is dangerous and expensive.
- Ask whether there is a vapor barrier under the slab. It decides whether a coated or resinous floor will stay down.
The roof will not carry what you plan to hang
Roof joists in a speculative building are designed with a small allowance for hung loads: sprinkler pipe, lights and little else. Overhead cranes, conveyors, bus duct, process piping and heavy ductwork exceed it quickly.
The structural engineer of record for the fit-out checks the existing joists and either reinforces them or carries the loads to the floor. Bridge cranes usually go on a free-standing runway with its own foundations. New rooftop equipment needs framing and curbs, and every roof penetration has to be made by the landlord's roofing contractor or the roof warranty is void, which the lease will say.
Fire protection was designed for a commodity you may not have
The roof sprinklers in a modern warehouse are an ESFR system, designed around stored goods in open floor space. Manufacturing changes the hazard, and construction inside the building changes the geometry.
- Any room, mezzanine or platform built inside obstructs the roof sprinklers and needs its own sprinklers beneath.
- Plastics processing, flammable liquids, spray finishing and oil-filled equipment each have their own protection requirements.
- Processes that generate combustible dust require a dust hazard analysis and, usually, explosion protection on the collection system.
- A shell fire alarm often monitors sprinkler water flow and nothing else. An occupied factory needs more.
If the process uses flammable or otherwise hazardous materials in quantity, the building classification itself is in question. That is the subject of control areas and H-occupancy, and it is checked before the lease, not during permit review.
Air, water and what leaves the building
Warehouses are ventilated, not conditioned. Process heat, make-up air for exhaust, and comfort cooling for a production workforce are all new mechanical scope, and they land on the roof structure discussed above.
- Gas, water and sewer capacity at the building were sized for a warehouse. Check each against the process demand.
- Process wastewater going to the city sewer needs an industrial discharge permit from the local utility.
- Air emissions from process equipment need authorization from the state environmental agency before the equipment is installed. Small sources often qualify for a streamlined path, but it still has to be confirmed first.
The lease is a construction document
Most of the items above are decided by the lease before a contractor is involved.
- Work letter and allowance. What the landlord pays for, who performs the work and whose contractor does it.
- Approval rights. How long the landlord has to approve drawings, and what happens if it takes longer.
- Restoration. Whether foundations, pits, mezzanines and the upgraded service must be removed at the end of the term.
- Rent commencement. A free-rent period is usually shorter than permit review plus construction plus equipment approval. Tie the date to the certificate of occupancy where you can.
Negotiate a due-diligence period and use it to collect the documents that answer the technical questions.
A two-week check before signing
- As-built drawings, including the structural drawings for the slab and roof.
- The geotechnical report used for the original design.
- The sprinkler design basis: the hydraulic data plate and the commodity it was designed for.
- The electrical one-line diagram and a written capacity statement from the utility.
- Water, sewer and gas capacity letters.
- The current certificate of occupancy and its occupancy group.
- Your own equipment list with weights, power, exhaust and the chemicals each machine uses.
With those in hand, a contractor can tell you within days whether the building works, what it costs to make it work, and how long it takes. Without them, everyone is estimating.
How CTECP works in the United States
CTECP works in the United States through CTECP INC, with locations in Houston, Dallas and Greenville, South Carolina. The group has delivered 250+ industrial projects and 580,000+ m² across 9 countries since 2016.
Fit-out of an existing building is the usual first step for manufacturers arriving from Asia and Mexico, and it is work we are set up for: machine foundations, power distribution, process utilities, rooms and mezzanines, delivered under one contract with licensed US subcontractors on the licensed trades. When the lease allows for it, we plan the fit-out so a later expansion does not undo it, as described in retrofit first, expand later.