Getting Power to a New US Manufacturing Plant: Load Letters, Service Studies, Transformers and the Dates the Utility Controls

2026-11-25 · CTECP — Global Design-Build General Contractor

On a US plant project the building is the part you can accelerate. Electric service is the part you cannot. It runs on the utility's engineering calendar, on a transformer the utility or you ordered months ago, and on an interconnection process that got stricter in Texas in 2025. Owners who treat power as a line item on the MEP budget discover it on the critical path in month ten. This guide lays out the sequence, what each step takes, where the owner has leverage and where there is none.

1. The load letter: the first document the utility will act on

Nothing happens at a utility until it has a written load request. The load letter states the parcel, the requested in-service date, the connected load and estimated peak demand in kW or kVA, the voltage you want, the largest motors and how they start, any process loads with poor power factor or harmonics, and a growth forecast. Larger utilities formalize this: Southern California Edison, for example, asks for a ten-year load schedule and a one-line diagram with its service application, and routes anything above 10 MW that wants a dedicated substation into a Method of Service study.

The letter does two things. It starts the utility's internal study clock, and it fixes the number the utility will design to. Understate the load to look small and the utility sizes a transformer you will outgrow; overstate it and you pay for capacity and may trigger a system study you did not need. Build it from the equipment list with nameplate data and a stated diversity factor.

2. The service study and what it decides

The utility's study answers four questions: which circuit or substation will feed you, at what voltage, what has to be built to get there, and who pays. For distribution-level service the assessment is typically a few months; SCE quotes about 90 days for its engineering assessment at that level. For loads that need a new substation or a transmission tap, the study is longer and may require a system impact analysis. The output is a service offer, often with a contribution in aid of construction for line extension or capacity, and a date.

The date in that offer is the date your plant can energize, regardless of when the building is done. Everything else in the project schedule should be read against it.

3. Primary vs secondary service and the customer-owned substation

Secondary service means the utility owns the transformer and delivers power at utilization voltage, typically 480/277 V, with the meter on the low side. Primary service means the utility delivers at distribution voltage, commonly 12.47 kV to 25 kV, and you own the transformer and everything downstream. Oncor's customer-owned primary guideline, for instance, delivers at 12.5 or 21.6 kV to a single customer-owned transformer bank with the meter on the load side. Primary service usually carries a lower energy rate and gives you control of the transformer order; it also makes you responsible for medium-voltage switchgear, protection and maintenance, and it puts the transformer lead time on your purchase order instead of the utility's.

Above a few megawatts the question becomes whether you want one customer-owned substation or several utility pad-mounts. Utilities differ in what they will offer at that scale, and the answer affects the plant layout: a substation needs a fenced yard, truck access and a cable or bus route into the building; multiple pad-mounts need concrete pads and clearances along the wall.

4. Transformers in 2026: the lead time that sets the schedule

Transformer delivery is the single longest lead item on most US industrial projects and it has not recovered. A Department of Energy review describes 36-month lead times as commonly quoted for large power transformers, with reported maximums near 60 months, against under a year before the pandemic. Wood Mackenzie's 2025 survey put large power transformers at an average of 128 weeks. Distribution-class units, which is what most plants need, are shorter but still long: industry trackers put 10 to 50 MVA units at roughly 52 to 78 weeks, and pad-mounted units remain the tightest category.

The practical consequence is that the transformer is ordered before the building permit, often before the design is final. Owners who wait for 100% drawings to release the transformer purchase order add a year to the plant. The same logic applies, with shorter but real lead times, to medium-voltage switchgear, the main switchboard and large VFDs.

5. Texas and ERCOT: what changed in 2025

Texas Senate Bill 6, signed in June 2025, created a new regime for large loads in ERCOT. It applies to new or expanded loads where the total demand at a single site would exceed 75 MW, a threshold the Public Utility Commission can lower. Those customers face uniform financial commitment requirements, must install equipment that lets ERCOT curtail the load directly during firm load shed, and face obligations around backup generation during emergencies. ERCOT's interim large-load process took effect in December 2025 and the PUCT's implementing rules were still proposed, not final, in March 2026.

Most manufacturing plants sit well under 75 MW and are not directly covered. Two things still matter. First, the large-load queue competes for the same substations and transformers your plant needs; a data center ahead of you on the same circuit changes your date. Second, municipally owned utilities and cooperatives may impose their own requirements on large customers, and some have. Outside ERCOT, in the regulated Southeast, the process is the utility's integrated planning and a certificate for new facilities, slower to start but with a single counterparty.

6. Backup power, power quality and the building

Backup generation is a code and a tariff question before it is an equipment question. A standby generator for life safety is governed by NEC Article 700 and sized small; a generator meant to carry process load needs the utility's approval of the transfer scheme, air permitting for the engine, and fuel storage that the fire marshal reviews. Battery storage sized to shave demand charges is increasingly common and brings NFPA 855 into the review. Power factor correction and harmonic filters are cheaper installed in the switchgear than bolted on after the first utility penalty.

On the building side, the service entrance, the electrical room and the transformer yard are fixed early because they drive the slab, the fire separation and the site plan. A medium-voltage switchgear room needs working clearances, a dedicated HVAC load and often a 2-hour rating. Locate it where the utility feed arrives and where the plant's largest loads are, not where the architect had space left.

7. How we run power on a US plant

We write the load letter in the first month, from the equipment list and a stated growth factor, and we carry the utility correspondence, the study, the service agreement and the long-lead package as a separate power schedule inside the project. The transformer and switchgear are released on their own approval. Electrical, mechanical and fire protection work is performed by licensed trade contractors under our management, with the utility's inspection and the AHJ's electrical inspection coordinated as one energization sequence.

CTECP works in the United States through CTECP INC, with locations in Katy (Houston), Dallas and Greenville, South Carolina. The group has delivered 250+ industrial projects and 580,000+ m² across 9 countries since 2016.

Planning a plant in Texas or the Southeast? Send us the equipment list and the parcel; we will tell you what to ask the utility for and which dates are theirs, not yours.

How we build in the US →
More insights
Industrial Construction in Texas: Permits, Licensed Trades and Power → Site Due Diligence for a US Industrial Parcel Before Closing → Tilt-Wall, Metal Building or Conventional Steel for a US Plant → Building a Plant in the United States as a Foreign Manufacturer →

Frequently asked questions

What is a utility load letter?

The owner's written request to the utility for electric service: site, in-service date, connected load and peak demand, voltage, largest motors, process loads and a growth forecast. It starts the utility's study and fixes the number the utility designs to. Some utilities formalize it with a ten-year load schedule and a one-line diagram.

How long does it take to get power to a new plant?

Distribution-level studies typically take a few months; a new feeder or substation can take a year or more. The transformer is usually the longest item: distribution-class units are quoted in the range of a year or more, and large power transformers at two to three years.

Primary or secondary service for a manufacturing plant?

Secondary: the utility owns the transformer and delivers at 480 V. Primary: you own the transformer and take delivery at distribution voltage, usually with a lower energy rate and more control, but with the switchgear, maintenance and the transformer lead time on your side. Compare on total cost of ownership.

Does Texas SB 6 apply to my plant?

Directly only if the load at a single site exceeds 75 MW, which most manufacturing plants do not. Indirectly, yes: large loads in the queue share the substations and transformers you need, and municipal utilities and cooperatives may add their own requirements.