On a US plant project the building is the part you can accelerate. Electric service is the part you cannot. It runs on the utility's engineering calendar, on a transformer the utility or you ordered months ago, and on an interconnection process that got stricter in Texas in 2025. Owners who treat power as a line item on the MEP budget discover it on the critical path in month ten. This guide lays out the sequence, what each step takes, where the owner has leverage and where there is none.
1. The load letter: the first document the utility will act on
Nothing happens at a utility until it has a written load request. The load letter states the parcel, the requested in-service date, the connected load and estimated peak demand in kW or kVA, the voltage you want, the largest motors and how they start, any process loads with poor power factor or harmonics, and a growth forecast. Larger utilities formalize this: Southern California Edison, for example, asks for a ten-year load schedule and a one-line diagram with its service application, and routes anything above 10 MW that wants a dedicated substation into a Method of Service study.
The letter does two things. It starts the utility's internal study clock, and it fixes the number the utility will design to. Understate the load to look small and the utility sizes a transformer you will outgrow; overstate it and you pay for capacity and may trigger a system study you did not need. Build it from the equipment list with nameplate data and a stated diversity factor.
- Send the load letter when you control the site, before design development; the utility's study runs in parallel with your drawings.
- State the in-service date you need, not the one you hope for, and ask the utility in writing whether it can meet it.
- Ask for the utility's service standards and the name of the project engineer in the same letter.
2. The service study and what it decides
The utility's study answers four questions: which circuit or substation will feed you, at what voltage, what has to be built to get there, and who pays. For distribution-level service the assessment is typically a few months; SCE quotes about 90 days for its engineering assessment at that level. For loads that need a new substation or a transmission tap, the study is longer and may require a system impact analysis. The output is a service offer, often with a contribution in aid of construction for line extension or capacity, and a date.
The date in that offer is the date your plant can energize, regardless of when the building is done. Everything else in the project schedule should be read against it.
- Ask whether the study assumes existing circuit capacity or a new feeder; a new feeder is the difference between months and a year.
- Get the contribution estimate broken down into line extension, transformer, metering and system upgrades.
- Ask what the utility will own and maintain and what you will; that line decides the next section.
3. Primary vs secondary service and the customer-owned substation
Secondary service means the utility owns the transformer and delivers power at utilization voltage, typically 480/277 V, with the meter on the low side. Primary service means the utility delivers at distribution voltage, commonly 12.47 kV to 25 kV, and you own the transformer and everything downstream. Oncor's customer-owned primary guideline, for instance, delivers at 12.5 or 21.6 kV to a single customer-owned transformer bank with the meter on the load side. Primary service usually carries a lower energy rate and gives you control of the transformer order; it also makes you responsible for medium-voltage switchgear, protection and maintenance, and it puts the transformer lead time on your purchase order instead of the utility's.
Above a few megawatts the question becomes whether you want one customer-owned substation or several utility pad-mounts. Utilities differ in what they will offer at that scale, and the answer affects the plant layout: a substation needs a fenced yard, truck access and a cable or bus route into the building; multiple pad-mounts need concrete pads and clearances along the wall.
- Compare primary and secondary on total cost of ownership, including switchgear, maintenance and the rate differential in the tariff, not on first cost.
- If you take primary service, order the transformer the week the utility confirms voltage; see the next section for why.
- Keep the substation yard and the service entrance off the expansion side of the building.
4. Transformers in 2026: the lead time that sets the schedule
Transformer delivery is the single longest lead item on most US industrial projects and it has not recovered. A Department of Energy review describes 36-month lead times as commonly quoted for large power transformers, with reported maximums near 60 months, against under a year before the pandemic. Wood Mackenzie's 2025 survey put large power transformers at an average of 128 weeks. Distribution-class units, which is what most plants need, are shorter but still long: industry trackers put 10 to 50 MVA units at roughly 52 to 78 weeks, and pad-mounted units remain the tightest category.
The practical consequence is that the transformer is ordered before the building permit, often before the design is final. Owners who wait for 100% drawings to release the transformer purchase order add a year to the plant. The same logic applies, with shorter but real lead times, to medium-voltage switchgear, the main switchboard and large VFDs.
- Release the transformer and main switchgear on a long-lead package with its own approval, separate from the construction contract.
- Ask the utility, if it owns the transformer, when it placed the order and from whom; its queue is your queue.
- Check the secondary market and refurbished units for the first unit only if the schedule cannot absorb the new-build lead time.
5. Texas and ERCOT: what changed in 2025
Texas Senate Bill 6, signed in June 2025, created a new regime for large loads in ERCOT. It applies to new or expanded loads where the total demand at a single site would exceed 75 MW, a threshold the Public Utility Commission can lower. Those customers face uniform financial commitment requirements, must install equipment that lets ERCOT curtail the load directly during firm load shed, and face obligations around backup generation during emergencies. ERCOT's interim large-load process took effect in December 2025 and the PUCT's implementing rules were still proposed, not final, in March 2026.
Most manufacturing plants sit well under 75 MW and are not directly covered. Two things still matter. First, the large-load queue competes for the same substations and transformers your plant needs; a data center ahead of you on the same circuit changes your date. Second, municipally owned utilities and cooperatives may impose their own requirements on large customers, and some have. Outside ERCOT, in the regulated Southeast, the process is the utility's integrated planning and a certificate for new facilities, slower to start but with a single counterparty.
- If your load is anywhere near 75 MW, or could reach it in phases, read the ERCOT process before signing the land contract.
- Ask the utility what else is in the queue on your circuit and substation.
- Treat a municipal utility or cooperative as a separate jurisdiction with its own service rules.
6. Backup power, power quality and the building
Backup generation is a code and a tariff question before it is an equipment question. A standby generator for life safety is governed by NEC Article 700 and sized small; a generator meant to carry process load needs the utility's approval of the transfer scheme, air permitting for the engine, and fuel storage that the fire marshal reviews. Battery storage sized to shave demand charges is increasingly common and brings NFPA 855 into the review. Power factor correction and harmonic filters are cheaper installed in the switchgear than bolted on after the first utility penalty.
On the building side, the service entrance, the electrical room and the transformer yard are fixed early because they drive the slab, the fire separation and the site plan. A medium-voltage switchgear room needs working clearances, a dedicated HVAC load and often a 2-hour rating. Locate it where the utility feed arrives and where the plant's largest loads are, not where the architect had space left.
- Decide standby versus process backup before the one-line is drawn; the transfer scheme changes the switchgear.
- Confirm the generator's air permit path with the state agency early; in Texas that is TCEQ.
- Size the electrical room for the second transformer and the next switchboard section.
7. How we run power on a US plant
We write the load letter in the first month, from the equipment list and a stated growth factor, and we carry the utility correspondence, the study, the service agreement and the long-lead package as a separate power schedule inside the project. The transformer and switchgear are released on their own approval. Electrical, mechanical and fire protection work is performed by licensed trade contractors under our management, with the utility's inspection and the AHJ's electrical inspection coordinated as one energization sequence.