An industrial park is sold as a real estate decision and lived as a utilities decision. The land price is the part that is easiest to compare and the least likely to determine whether your plant opens on time.
Ask about capacity to your lot, not capacity to the park
Every park brochure states an electrical capacity. It is almost always the capacity of the park's substation, not the capacity that can be delivered to your lot, on your date, after the other tenants already committed are served.
Three questions turn a brochure figure into a usable one:
- How much is currently uncommitted? A park at 80% occupancy has already allocated most of what it had.
- What does it take to get it to my lot? Medium-voltage feeder, substation extension, or a dedicated transformer — each is a different cost and a different calendar.
- Will you put it in writing with a date? This is the question that separates a real answer from a sales answer.
BOX:For a plant with significant electrical demand, the CFE connection process is routinely the critical path — longer than the building itself. A park that has resolved this is worth a land premium that looks irrational on a spreadsheet.
Water and discharge are a permitting question, not a plumbing one
Water supply in several northern Mexican regions is genuinely constrained, and the constraint shows up as an allocation question and an effluent-permitting question rather than as a pipe.
What to establish before committing:
- Allocation available to your lot, in writing, in the volume your process needs
- Where treated effluent goes, and whether your discharge characteristics are within what the park's system accepts
- Whether you will need your own pretreatment — a building, a budget and a permit on its own
- Rainwater retention requirements, which affect how much of your lot is actually buildable
For a water-intensive process this can disqualify an otherwise excellent site, and it is far cheaper to discover now than after the land is bought.
The rules you cannot change after you sign
Parks operate under covenants. They are normal and usually reasonable, but they are frozen from your side and several of them have direct construction consequences:
| Setbacks, height and coverage | Determine how much of your lot is actually buildable and whether a future phase fits. Check this against a real massing, not a percentage. |
| Architectural and façade rules | Some parks mandate finishes or colours. A minor cost, but one that belongs in the budget rather than in a change order. |
| Expansion rights | Whether an adjacent lot can be reserved, for how long and at what price. If phase two is part of the plan, this clause is worth more than a land discount. |
| Operating hours and truck access | Affects shift patterns and inbound logistics; occasionally affects whether 24-hour operation is possible at all. |
| Common-area fees | What they cover, how they escalate, and what happens when the park builds new infrastructure you do not use. |
What the land price does and does not include
| Item | Often included | Often not — ask |
|---|---|---|
| Paved access to the lot line | ✔ | |
| Electrical connection point | To the lot line | The feeder, transformer and the capacity increase |
| Water and sewer connection | To the lot line | Allocation volume; pretreatment |
| Gas | Sometimes | Distance to the nearest line, and who pays to extend it |
| Fibre / telecom | Usually | Redundant path, if you need one |
| Land-use certificate | Usually | Specific use for your process |
| Site grading | Rarely | Cut and fill balance on your lot |
| Rainwater retention | Park-level | On-lot requirement |
The right-hand column is where comparable-looking lots stop being comparable.
Certifications, security and the things auditors ask about
If you will export to the US or operate under a corporate compliance regime, some of this becomes a procurement requirement rather than a preference:
- Customs and security programmes relevant to cross-border shipping — ask which the park and its tenants hold, and what it requires of you
- Perimeter control, access logging and whether security is park-operated or outsourced
- Whether the park has experience with tenants under IMMEX, and how bonded operations are handled physically on site
- Environmental and fire-safety track record — specifically, has the park's infrastructure been tested by an actual incident
Park versus standalone land
A park is substantially a purchase of resolved schedule risk: utilities, access, zoning and often a faster permit path, in exchange for a land premium and rules you did not write.
Standalone land can be considerably cheaper and gives full control, but utility connections, access and zoning become your project — and for a high-demand plant that usually means the electrical connection becomes the schedule.
The honest rule of thumb: the stronger your schedule constraint and the higher your electrical demand, the more a park is worth. The longer your horizon and the more unusual your facility, the more standalone land makes sense.
The questions to take to the park
- Uncommitted electrical capacity today, what reaching my lot requires, and will you put a date in writing?
- Water allocation available to my lot, and what my discharge characteristics must be?
- Covenants: setbacks, height, coverage, façade, hours, truck access — in full, before we price anything.
- Expansion: can an adjacent lot be reserved, for how long, at what price?
- What is included to the lot line, and what is on my side of it?
- Common-area fees: current, escalation mechanism, and what new infrastructure triggers.
- Which permits has the park already resolved, and which remain mine?
A park that answers these in writing and quickly is demonstrating something about how it will behave during construction. One that answers in brochures is also telling you something.
Where we come in
We are not brokers and do not sell or represent parks. What we do is the technical review behind these questions — translating a park's answers into what they mean for your building, your programme and your budget, before the land commitment is made.
That work sits in preconstruction: available capacity, water and discharge, permit route, buildable area against a real massing, and a defensible cost range. It is the cheapest place in the whole project to discover a bad site.