In distribution facilities the expensive decisions are made before the slab is poured, and most of them are about geometry: how high you can stack, how flat the floor is, how many trucks can turn at once. None of the three can be fixed afterwards.
Building in the United States instead? See our guide to distribution center construction in the US.
Site development: the half of the project that is not the building
A distribution center is a building sitting inside a truck yard, and the yard usually drives more of the cost and the schedule than people expect. What gets decided here:
| Truck court depth | Governed by the longest vehicle that will use it. A standard tractor-trailer needs roughly 130 ft (≈40 m) of apron to back square into a dock without a second pull-up. Cut this and every delivery becomes a two-move operation for the life of the building. |
| Trailer parking and staging | Counted separately from truck court. If drop-and-hook is part of the operation, the stall count is an operational input, not an architectural one — ask the logistics team, not the architect. |
| Grading and retention | The pad usually has to be flat, the site usually is not, and stormwater has to be retained somewhere. Cut and fill balance is one of the few line items that can move a budget by a visible percentage. |
| Access and turning radius | Entry geometry, gate stacking depth so arriving trucks do not queue onto the public road, and guard house position. |
A useful early question: how many trailers must be on site at the busiest hour, and how many of them are moving? That one answer sizes the yard, and the yard sizes the land.
Clear height is an economic decision, not an architectural one
Clear height — the usable height under the lowest obstruction, not the eave height — sets how many pallet positions the same footprint yields. Going higher costs more in structure, in sprinklers and in racking, and it buys storage that would otherwise require more land and more roof.
The crossover depends on land price, product density and how long you intend to hold the building. It is a financial model, not a rule of thumb — and it has to be run before the structure is designed, because the frame, the sprinkler design and the slab thickness all follow from it.
Two things that quietly eat clear height after the fact: sprinkler mains and lighting run below the structure instead of between the joists, and HVAC or process services added later with no reserved route.
Slab: flatness is specified for the equipment, not in general
Floor flatness and levelness requirements are driven by the lift truck and racking configuration you actually intend to operate:
- Conventional counterbalance and reach trucks — ordinary random-traffic flatness is normally adequate.
- Very narrow aisle (VNA) with wire or rail guidance — defined-traffic flatness along the aisle, which is a different specification, a different construction method and a different price.
- Automated systems (AS/RS, shuttles) — tolerances come from the equipment vendor and are typically tighter than any building standard.
Deciding the racking after the slab is poured is the expensive order. If the operation may move to VNA later, that has to be stated now, even if the first fit-out is conventional.
Also set at slab stage: joint type and spacing, load capacity under rack posts (a point load, not a uniform load), and surface hardening appropriate to wheel traffic.
Docks, fire protection and column grid
| Dock ratio | Doors per unit of floor area is an operational number: a cross-dock facility and a storage warehouse with the same footprint need very different door counts. Specify levelers, seals or shelters, and restraints as part of the same decision. |
| Fire protection | ESFR (early suppression fast response) from the ceiling versus in-rack sprinklers is one of the biggest cost forks, and it is driven by commodity classification and storage height — i.e. by what you store, not by the building. Changing stored commodity class later can invalidate the design. |
| Column grid | Wider bays cost more structurally and buy racking flexibility and fewer obstructions in aisles. The grid should be laid out against a real rack layout, not chosen as a round number. |
| Roof and insulation | Drives both the cold chain (if any) and the ongoing energy bill; also where future solar loading has to be anticipated if that is on the roadmap. |
What is specific to Mexico
- Electrical supply. The CFE connection process runs on its own calendar and is independent of construction. For a facility with significant refrigeration or automation, the power request should be filed in the first weeks of the project — otherwise the building is finished and cannot be commissioned.
- Permits. Municipal construction licence, land-use confirmation, and the environmental path if the operation triggers it. These run in parallel but their sequence cannot be reordered.
- Customs-bonded operation. If the facility will operate under IMMEX or as a bonded warehouse, the layout, access control and record-keeping requirements affect the building design and must be known before layout is frozen — not added afterwards.
- Seismic and wind zone. Varies widely by region and changes the structure and the rack anchorage; racking in a high seismic zone is a structural engineering item.
How we work on these
We deliver distribution and logistics facilities under design-build or EPC: site development, structure, envelope, slab, docks, fire protection and MEP under a single contract, with the scope list and the exclusions written into the proposal.
What we do not do: we are not the racking or automation supplier and do not qualify material handling systems. We coordinate with the vendor you select and deliver the building conditions their equipment requires — slab tolerance, power, anchorage and clearances — as a written, verifiable interface.
Building the US end of the same network? North of the border the drivers change: fire-code permits for high-piled storage, tilt-wall construction and state-licensed trades. See distribution center construction in the United States.
