Most cleanroom disputes are not about workmanship. They are about a specification that was never complete enough to be met — and the gap shows up on the day someone tries to hand the room over.
What an ISO class tells you, and what it does not
ISO 14644-1 classifies a room by airborne particle concentration. What it does not do by itself is say when that concentration has to hold — and that is the entire commercial question.
| As-built | Construction complete, equipment installed but not running, no people. The easiest state to achieve, and the one a weak specification implicitly accepts. |
| At-rest | Equipment installed and running, no people present. A meaningful commitment, and the one most industrial projects should be contracting for. |
| Operational | Equipment running and people working. The hardest, because people are the dominant particle source, and it depends on gowning, behaviour and headcount — things a contractor does not control after handover. |
⚠️ «The room shall be ISO 7» is not a specification. «ISO 7 at-rest, verified by the following test, with this number of sample points» is. Without the state and the test method, two bidders can price work that differs by a wide margin and both be technically responsive.
BOX:It follows that the acceptance criteria belong in the tender documents, not in the commissioning plan. A criterion agreed after the work is built is a negotiation, not a test.
The pressure cascade is the decision you cannot revisit
Cleanliness is maintained by air moving in one direction — from clean toward less clean — and never the other way. That cascade is designed once and built into the layout. Changing it later means moving walls and redoing ductwork, because it is a consequence of the room sequence, not a setting on a controller.
- Door interlocks and airlock sequencing are part of the design, not an accessory. Two doors of an airlock open at once is a cascade failure, and operations will cause it daily unless the design prevents it.
- Material and personnel routes should be separate, and drawn, before the layout is fixed. Retrofitting a material airlock into a finished suite is close to rebuilding it.
- Containment reverses the logic. If the process is hazardous, air must flow into the room rather than out of it — a different design, and one that cannot be bolted onto a cascade designed the other way.
- Differential pressure monitoring and alarms are what make the cascade auditable later. Without recorded data there is no evidence the room ever held.
Above the ceiling is where the work actually is
A walk-through sells the panels. The performance lives in the plenum, which nobody looks at.
- Every penetration is a leak path — sprinklers, lights, ducts, cable trays, sensors. The sealing detail and who is allowed to make a new penetration after handover decide whether the room still performs in year three.
- Terminal filter housings have to be accessible for testing and change-out without dismantling the ceiling. This is designed in or it is not available.
- Walkable versus non-walkable ceilings is a maintenance decision with a structural consequence, and it has to be made before the grid is specified.
- Return air paths are as important as supply, and are the part most often under-designed because they are invisible on a plan.
Three issues specific to building in Turkey
| TBDY 2018 governs more than the frame | The Turkish seismic code addresses non-structural components, not only the primary structure. For a cleanroom that means ceiling grids, suspended ductwork, hanging equipment and partition anchorage have to be engineered and braced, not simply hung. This is one of the most common gaps when a cleanroom is designed abroad and built in Turkey. |
| The contractor authorisation certificate | Construction work in Turkey requires the contractor to hold a Yapı Müteahhitliği Yetki Belgesi, and the authorisation number has to appear on the building permit (yapı ruhsatı), on the occupancy permit (yapı kullanma izin belgesi) and in the construction contract. Verify this before signing, not at permit stage — an owner who discovers the gap later has a permit problem, not a procurement problem. |
| Imported components and lead time | Filters, air handling units, control systems and specialist panels are frequently imported. Customs documentation and lead time belong in the programme from the first week, and the specification should say what substitution is acceptable — because the substitution will be proposed, under schedule pressure, by whoever is fastest. |
Handover: evidence, not good intentions
A cleanroom is handed over with a document set or it is not handed over.
- Installed filter leak testing at each terminal — the test that proves the filter and its housing seal, which is a different question from whether the filter itself is good
- Airflow volume and uniformity against the design, measured and recorded per location
- Room pressure differentials across every boundary in the cascade, in the stated occupancy state
- Particle counts at the agreed class, in the agreed state, with the sample plan agreed in advance
- Recovery test — how quickly the room returns to class after a disturbance, which is the test that most resembles real operation
- As-built documentation, with what was field-verified distinguished from what was assumed from design
⚠️ Agree the sample plan before testing. A particle count with the points chosen after a disagreement has started is not evidence to anyone.
Where validation responsibility sits
For regulated products, the contractor's testing above is commissioning. It is not validation.
IQ, OQ and PQ belong to the owner and the owner's validation consultant, against the owner's own quality system. A contractor builds and documents so that qualification can proceed; a contractor does not qualify the facility and does not sign for it. Any contractor offering to deliver a validated facility is describing something they cannot be accountable for, because validation is a judgement made inside the owner's quality system.
⚠️ Settle this in the contract. It is the single most common source of dispute at handover on regulated projects, and it is free to resolve beforehand.
What we do, and what we do not
We design and build cleanrooms and controlled environments as part of a single contract covering the shell, envelope, flooring, MEP and the clean envelope itself, and we hand over with the test records listed above.
Our delivered classification experience is ISO 8 at-rest. We do not hold a track record in sterile Grade A/B pharmaceutical manufacturing and we do not present ourselves as a turnkey general contractor in that segment. For a project at that level, the right contractor is one who can show comparable completed work — and you should ask us for the same evidence you ask of anyone else.
On Turkey specifically: our Turkish entity was established at the end of 2025. Its registration details are public and verifiable, and we would rather you check them than take a claim on trust. Where a project requires a contractor track record in Turkey longer than ours, we will say so rather than bid around it.