Türkiye is straightforward to build in once you know three things that differ from most other markets: who is legally allowed to be named as the contractor, how the permit chain ends, and how much of the structural design is driven by seismic code.
The contractor authorisation number — a prerequisite, not a credential
Under the Turkish regulation on the classification and registration of building contractors, every structure requiring a building permit must be built under the responsibility of a contractor holding a Yapı Müteahhitliği Yetki Belgesi Numarası — an authorisation number held in the ministry's registry system.
The number is not a certificate on a wall. It is required to appear on three documents:
- the building permit (yapı ruhsatı)
- the occupancy permit (yapı kullanma izin belgesi)
- the construction contract itself
BOX:The practical consequence for a foreign investor: a contractor without this number cannot legally be named on your permit, which means the project cannot start in their name and cannot be signed off at completion. Ask for the number before you shortlist, not before you sign.
Contractors are graded from A to H on financial, professional and technical capacity, and the grade limits the scale of work that can be undertaken. A number alone is therefore not sufficient — ask which class, and what that class permits. In a joint venture each partner must hold its own number and a further number is obtained for the venture itself.
The permit chain, and where projects actually stall
| Yapı ruhsatı (building permit) | Issued by the municipality, against an approved project. This is where land use, zoning and the fire design are checked. |
| Construction | Carried out under the named contractor's authorisation number, with a site supervisor (şantiye şefi) registered to the project. |
| Yapı kullanma izin belgesi (occupancy) | Required before production can start. The as-built condition is checked against the approved project — most commonly fire compartmentation and smoke extraction, which process partitions and mezzanines change. |
| Operating approvals | Sector-specific registrations and, where applicable, environmental process. These run on their own calendar, in parallel. |
Projects rarely stall in construction. They stall because occupancy cannot be issued against an as-built that diverged from the approved drawings, or because an operating approval was started too late.
TBDY 2018: more of the design than foreign teams expect
Türkiye's seismic code governs not only the structural frame but the non-structural elements that industrial projects are full of:
- Suspended ceiling systems
- Duct and pipe hangers
- Racking and storage systems
- Equipment anchorage and skid restraint
A factory design prepared in another country cannot be applied directly. Those details are recalculated, and in high-seismic regions racking in particular becomes a structural engineering item rather than a supplier catalogue item.
This is worth budgeting for at feasibility stage. Discovering it during detailed design costs schedule, not just fees.
Organised industrial zone or standalone land
| OSB (organised industrial zone) | Utilities, access and zoning are generally resolved, which removes a large block of schedule risk. In exchange: land premium, zone rules on what may be manufactured, and in some zones an allocation process rather than an open purchase. |
| Standalone land | Can be cheaper and allows more freedom, but utility connections, access and zoning become your project. For a plant with significant electrical demand this frequently decides the completion date. |
The difference between the two is mostly schedule risk, not price. A foreign investor underwriting a production start date should weight it accordingly.
What actually sets the schedule
- Electricity connection and capacity. Independent of construction and frequently the controlling item for high-demand plants. Start it in the first weeks.
- Long-lead equipment. Transformers, switchgear, chillers, air handling units, cranes. Ordered backwards from delivery time, not forwards from the construction programme.
- Permits. Parallel, but in a fixed sequence that cannot be reordered.
- Freezing the equipment layout. Foundations, service routes and pits cannot be frozen until the production equipment layout is. In most projects this single owner-side decision defines the critical path.
A programme that does not show the electricity connection and long-lead equipment as separate lines is a construction programme, not a project programme.
Contract models
The same factory can be contracted traditionally (design, then tender), as design-build, or as EPC with a fixed price and date. The price difference is usually smaller than expected; the real difference is who carries the consequences when something is missing from the documents.
One rule holds across all three: a fixed price implies a fixed scope. A fixed-price contract with an underdefined scope is not a fixed price — it is a deferred dispute. The exclusions list is where proposals should be compared, not the headline number.
How we work in Türkiye
Work in Türkiye is contracted through CTECP İnşaat Limited Şirketi, our registered Turkish entity in İstanbul. Trade registry and tax identifiers are listed openly on our Türkiye page so they can be verified before any conversation about scope.
What we do: civil and steel structure, controlled environments up to ISO 8 at-rest, HVAC and process services, mechanical and electrical installation, and a closeout package with as-builts, material certificates and test protocols.
What we do not: we have no track record in sterile pharmaceutical manufacturing (Grade A/B) and do not present ourselves as a turnkey contractor in that space. Where a contract scope requires a contractor authorisation of a particular class, we raise which party holds it before signature — we bring it up ourselves at proposal stage rather than leaving it to be discovered.