Building a Factory in Turkey: A Design-Build / EPC Guide

2026-07-01 · CTECP — Global Design-Build General Contractor

Türkiye is straightforward to build in once you know three things that differ from most other markets: who is legally allowed to be named as the contractor, how the permit chain ends, and how much of the structural design is driven by seismic code.

The contractor authorisation number — a prerequisite, not a credential

Under the Turkish regulation on the classification and registration of building contractors, every structure requiring a building permit must be built under the responsibility of a contractor holding a Yapı Müteahhitliği Yetki Belgesi Numarası — an authorisation number held in the ministry's registry system.

The number is not a certificate on a wall. It is required to appear on three documents:

BOX:The practical consequence for a foreign investor: a contractor without this number cannot legally be named on your permit, which means the project cannot start in their name and cannot be signed off at completion. Ask for the number before you shortlist, not before you sign.

Contractors are graded from A to H on financial, professional and technical capacity, and the grade limits the scale of work that can be undertaken. A number alone is therefore not sufficient — ask which class, and what that class permits. In a joint venture each partner must hold its own number and a further number is obtained for the venture itself.

The permit chain, and where projects actually stall

Yapı ruhsatı (building permit)Issued by the municipality, against an approved project. This is where land use, zoning and the fire design are checked.
ConstructionCarried out under the named contractor's authorisation number, with a site supervisor (şantiye şefi) registered to the project.
Yapı kullanma izin belgesi (occupancy)Required before production can start. The as-built condition is checked against the approved project — most commonly fire compartmentation and smoke extraction, which process partitions and mezzanines change.
Operating approvalsSector-specific registrations and, where applicable, environmental process. These run on their own calendar, in parallel.

Projects rarely stall in construction. They stall because occupancy cannot be issued against an as-built that diverged from the approved drawings, or because an operating approval was started too late.

TBDY 2018: more of the design than foreign teams expect

Türkiye's seismic code governs not only the structural frame but the non-structural elements that industrial projects are full of:

A factory design prepared in another country cannot be applied directly. Those details are recalculated, and in high-seismic regions racking in particular becomes a structural engineering item rather than a supplier catalogue item.

This is worth budgeting for at feasibility stage. Discovering it during detailed design costs schedule, not just fees.

Organised industrial zone or standalone land

OSB (organised industrial zone)Utilities, access and zoning are generally resolved, which removes a large block of schedule risk. In exchange: land premium, zone rules on what may be manufactured, and in some zones an allocation process rather than an open purchase.
Standalone landCan be cheaper and allows more freedom, but utility connections, access and zoning become your project. For a plant with significant electrical demand this frequently decides the completion date.

The difference between the two is mostly schedule risk, not price. A foreign investor underwriting a production start date should weight it accordingly.

What actually sets the schedule

A programme that does not show the electricity connection and long-lead equipment as separate lines is a construction programme, not a project programme.

Contract models

The same factory can be contracted traditionally (design, then tender), as design-build, or as EPC with a fixed price and date. The price difference is usually smaller than expected; the real difference is who carries the consequences when something is missing from the documents.

One rule holds across all three: a fixed price implies a fixed scope. A fixed-price contract with an underdefined scope is not a fixed price — it is a deferred dispute. The exclusions list is where proposals should be compared, not the headline number.

How we work in Türkiye

Work in Türkiye is contracted through CTECP İnşaat Limited Şirketi, our registered Turkish entity in İstanbul. Trade registry and tax identifiers are listed openly on our Türkiye page so they can be verified before any conversation about scope.

What we do: civil and steel structure, controlled environments up to ISO 8 at-rest, HVAC and process services, mechanical and electrical installation, and a closeout package with as-builts, material certificates and test protocols.

What we do not: we have no track record in sterile pharmaceutical manufacturing (Grade A/B) and do not present ourselves as a turnkey contractor in that space. Where a contract scope requires a contractor authorisation of a particular class, we raise which party holds it before signature — we bring it up ourselves at proposal stage rather than leaving it to be discovered.

Planning an industrial project in Turkey? Let's Build Your Dream.

Get a Quote →
More insights
Türkiye'de Fabrika İnşaatı (TR) → Cleanroom Construction in Turkey →

Frequently asked questions

What is a Yapı Müteahhitliği Yetki Belgesi and why does it matter to me?

It is the contractor authorisation number held in the Turkish ministry's registry. Every structure requiring a building permit must be built under the responsibility of a contractor holding one, and the number must appear on the building permit, the occupancy permit and the construction contract. A contractor without it cannot legally be named on your permit. Contractors are graded A to H and the grade limits the scale of work permitted, so ask which class, not just whether they have a number.

Can I build in Türkiye using a design prepared in another country?

Not directly. At minimum three areas are reworked: TBDY 2018 seismic detailing — which covers suspended ceilings, duct and pipe hangers, racking and equipment anchorage, not only the frame; fire compartmentation and smoke extraction matching the approved project, since the as-built is checked against it at occupancy; and the building permit and occupancy process itself. Budget for this at feasibility stage.

Organised industrial zone or standalone land?

An OSB generally has utilities, access and zoning resolved, which removes a large block of schedule risk, at the cost of a land premium, zone rules on what may be manufactured and sometimes an allocation process. Standalone land can be cheaper and freer but makes utility connections, access and zoning your project. The difference is mostly schedule risk rather than price.

What usually controls the completion date?

Four things, rarely the construction itself: the electricity connection and capacity request, which is independent of construction and often controls high-demand plants; long-lead equipment such as transformers, switchgear, chillers and cranes; the permit sequence; and the owner freezing the production equipment layout, since foundations, service routes and pits cannot be fixed until it is.

Which contract model should I use?

Traditional, design-build and EPC differ less in price than in who carries the consequences when something is missing from the documents. The rule that holds across all three is that a fixed price implies a fixed scope — a fixed-price contract over an underdefined scope is a deferred dispute. Compare proposals on the exclusions list, not the headline number.