Once a plant's demand crosses into medium voltage, the utility delivers power to a point and everything after that point is yours to build, own, protect and maintain. That boundary is where a surprising amount of project risk lives.
Where the utility stops and you begin
At low voltage the utility essentially hands you usable power. At medium voltage — which covers most industrial plants — it delivers to a connection point and you own the transformation and distribution:
- Medium-voltage switchgear and protection
- Transformer or transformers
- Low-voltage main distribution, panels and feeders
- Metering arrangement per the utility's requirements
- Grounding and bonding system
- The civil works, enclosure and clearances around all of it
BOX:This boundary should be drawn explicitly in your construction contract. «Electrical connection» is one of the most commonly ambiguous scope lines in Mexican industrial tenders, and the gap between what the utility does and what the contractor does is exactly where variations appear.
Transformer: sizing, type and the delivery problem
| Sizing | Driven by demand, not connected load, with a growth allowance you can justify. The same discipline as the service request: a defined future state, not an imagined one. Oversizing costs capital and runs the unit inefficiently at low load. |
| Oil-filled vs dry type | Oil units are generally more efficient and cheaper per kVA but bring fire separation, containment and maintenance obligations. Dry type costs more and simplifies siting, particularly indoors or near occupied areas. This is a siting decision as much as an electrical one. |
| Lead time | Transformers and switchgear have been among the longest-lead items in industrial projects in recent years. Order dates are set backwards from required delivery, not forwards from the construction programme — and in practice this item often has to be ordered before the building design is complete. |
| Delivery and placement | A transformer is a heavy-haul item. Route access, crane or jacking provisions, and the pad have to be planned, not improvised. Replacing one later through a finished building is a demolition exercise. |
Protection and coordination — the part nobody sees until it matters
A protection scheme has to do two things that pull against each other: clear a fault fast enough to protect equipment and people, and be selective so that only the affected section trips.
Poor coordination shows up as a fault on one machine taking down an entire production hall. It is not detectable by inspection — it is a calculation.
- Short-circuit study — fault levels at each point, which sets equipment ratings
- Coordination study — relay and breaker settings so upstream devices wait for downstream ones
- Arc flash study — incident energy, which determines PPE requirements and labelling for whoever will operate the plant
These studies should be deliverables named in the contract. They are routinely omitted from scope and then missing when the operations team asks for them.
Power factor and harmonics: two ongoing costs set at construction
| Power factor | Mexican industrial tariffs penalise low power factor and can reward a high one. Correction equipment is inexpensive relative to the penalty over a plant's life, and the space for it is far cheaper to reserve now than to find later. |
| Harmonics | Variable frequency drives, rectifiers and switching power supplies inject harmonic currents. In a modern plant with many drives this is not a theoretical concern — it causes transformer heating, neutral overloading and nuisance tripping. Mitigation is a design decision (drive selection, reactors, filters), not a later fix. |
| Metering and monitoring | Sub-metering by area or by line costs little at construction and is the only way to attribute consumption afterwards. Retrofitting it means working on live distribution. |
Grounding, lightning and continuity
Grounding is specified for the whole installation, not improvised per building: earthing grid, equipment bonding, separately derived systems, and the interface with the utility's arrangement.
Two items commonly under-scoped:
- Lightning protection — regional exposure varies widely across Mexico and should be assessed rather than assumed either way.
- Sensitive-equipment earthing — instrumentation, controls and clean-power requirements for process equipment. The equipment vendor's requirements have to reach the electrical designer before the system is built, not after.
NOM-001-SEDE and the verification that gates energisation
Electrical installations in Mexico are governed by NOM-001-SEDE, the official standard for electrical installations. For industrial service, the installation must be verified by an approved verification unit (unidad de verificación de instalaciones eléctricas), which issues the dictamen confirming compliance.
🔴 This is a gate, not a formality. Without it the service is not energised — a finished, tested, perfectly good installation sits dark.
What it means in practice:
- The verification unit is engaged during the project, not after everything is closed up — observations are far cheaper to correct before walls and ceilings are finished
- The as-built documentation must match what was installed, because that is what is verified
- Any deviation from the approved design needs to be reflected, not quietly absorbed
Ask any electrical contractor who handles the verification and when they plan to engage it. A vague answer here reliably predicts a delay at energisation.
What should be in the handover package
- Single-line diagram, as-built
- Short-circuit, coordination and arc flash studies
- Protection settings as actually commissioned
- Transformer and switchgear test reports (factory and site)
- Grounding resistance measurements
- NOM-001-SEDE verification dictamen
- Equipment manuals, spare parts list and maintenance training
As with every other discipline, these are created during the work or not at all. A relay settings file reconstructed two years later by a different team is not the same document.
How we scope electrical work
We take plant electrical infrastructure within design-build and EPC contracts: medium-voltage substation, distribution, protection studies, grounding and the process connections, with the boundary to the utility drawn explicitly in the proposal.
Two things we treat as separate programme lines rather than construction subtasks, because they behave differently: long-lead equipment (transformer and switchgear, ordered off delivery dates) and verification and energisation (engaged early, not at the end). Those two items are where electrical scope usually slips, and neither is solved by working faster on site.