Owners select contractors the way they were taught to select suppliers: lowest qualified bid. For a design-build plant that method fails, because the design is not done when the price is given and the contractor is selling judgment, not a part number. The eight questions below are what an experienced owner's representative asks, in the order that eliminates candidates fastest. The answers you want are specific, written and sometimes unflattering.
1. Who holds the licenses, and in which state?
There is no federal contractor license. Some states license general contractors; Texas does not, and instead licenses the trades: electrical and HVAC through the Texas Department of Licensing and Regulation, plumbing through the state plumbing board, fire sprinkler and alarm through the state fire marshal. Other states license the general contractor as well, with reciprocity that is partial at best. A contractor that is licensed where it is headquartered is not automatically able to pull permits where your plant will be.
- Ask for the license numbers, in your state, of the general contractor (where required) and of the electrical, plumbing, mechanical and fire-protection contractors it intends to use.
- Ask who will be the licensed professional engineer of record for each discipline and in which state they are registered.
- Ask what the contractor self-performs and what it subcontracts; a design-builder that self-performs nothing is a manager, which can be fine, but the price should reflect it.
2. What is the bonding capacity, and who is the surety?
Performance and payment bonds are how an owner knows a contractor can finish and that subcontractors will be paid. A surety's letter stating the contractor's single-project and aggregate bonding capacity is a credit decision by a third party that has seen the contractor's financial statements. A capacity below your contract value, or a surety that is not rated, is a disqualifier, not a negotiation point.
- Require a surety letter with single and aggregate limits, dated within the last 90 days.
- Decide whether you will require bonds on the full contract; the premium is real money and the decision belongs in the RFP.
- Ask whether the design professional carries professional liability separately from the contractor's CGL; design-build blurs the line and the insurance should not.
3. Which insurance, at what limits?
The standard set is commercial general liability, workers' compensation, automobile, umbrella or excess liability, builder's risk for the project, and professional liability for the design. Limits are set by the owner's risk manager, not by the contractor's broker; the certificate of insurance should name the owner as additional insured and show the limits, the carriers and the expiration dates. Imported equipment and foreign-registered design staff raise questions a domestic broker may not have seen; ask them early.
- Set the required limits in the RFP and ask for certificates with the proposal, not after award.
- Decide who buys builder's risk; the owner often gets a better rate and keeps control of the claim.
- Confirm workers' compensation covers every entity that will have people on site, including the design-builder's own foreign staff.
4. Which contract form, and what does it say about the price?
The two common families are the AIA design-build documents, where A141-2024 is the current owner and design-builder agreement, and the DBIA standard forms. A141 is built in two stages: an agreement for preliminary work, then a Design-Build Amendment signed when the contract sum is set, with Exhibit A covering insurance and bonds. Both families support a guaranteed maximum price with shared savings or a lump sum. The form matters less than the owner understanding, before signing, when the price becomes fixed and what is excluded from it.
- Ask the contractor which form it proposes and for a redline of its usual modifications; the modifications tell you more than the form.
- Under a GMP, agree the contingency ownership and the audit rights in writing; under a lump sum, agree the exclusions list line by line.
- Define the design-basis documents that fix the price, and the change-order rule for everything the owner adds after them.
5. GMP or lump sum, and when?
A guaranteed maximum price fits a project whose design is still moving: the owner sees the cost build-up, shares savings, and carries less risk of a padded number. A lump sum fits a project whose design basis is frozen and whose owner wants one number and no audit. The wrong choice is the one made for the wrong reason: lump sum to avoid paying for design, or GMP to avoid committing to a scope. Either way, the price should be set only when the long-lead items, the utility service offer and the permitting path are known.
- Do not fix the price before the utility has answered the load letter and the transformer lead time is known.
- Ask for the cost breakdown by division under either model; a contractor that will not show its structure is telling you something.
- Agree the allowances and the unit rates for the items that will change: rock, dewatering, imported equipment interfaces.
6. Who controls the schedule, and does the contractor know it?
On a US plant the owner can accelerate the building and cannot accelerate the utility, the permit office or the transformer factory. A contractor that promises a date without a load letter, a permit path and a long-lead procurement plan is promising on your behalf. The right answer to a schedule question is a schedule with the external dependencies named and dated.
Look at how the proposal treats the first ninety days. A contractor that has built plants recently will show the load letter, the zoning confirmation, the platting application and the long-lead releases in the first month, in parallel with design. One that shows design first and everything else after it has not been burned yet, and will be on your project. The same applies to the permit path: a schedule that shows a single bar for permitting, rather than the building permit, the trade permits, the state reviews and the certificate of occupancy as separate items, was drawn by someone who has not sat in the plan-review queue.
- Ask for a proposal schedule that shows the utility, permitting and long-lead items as separate lines with owners.
- Ask what the contractor did on its last two projects when the transformer slipped; the answer reveals whether it has lived through it.
- Ask which permits the contractor will apply for in its own name and which require the owner's.
7. The references that matter
Every contractor has three happy references. Ask for a different set: the last project of similar size in your state, the last project where the contractor had a claim or a dispute, and the owner's representative on both, by name. Then ask the subcontractors, because licensed electrical and mechanical subcontractors know which general contractors pay on time and which run a clean site, and they talk.
- Call the trade subcontractors the contractor listed for your project and ask about payment and change-order behavior.
- Visit a project under construction, not a finished one; a site tells you how the contractor manages safety and sequence.
- Ask the contractor's bank or surety, with permission, how long the relationship has lasted.
8. For a foreign owner: the extra question
A plant built for an overseas parent has one more requirement: the contractor must be able to explain US rules to a headquarters that has never built here, in writing, in the parent's working language, without flattening the differences. Imported production lines need NRTL field evaluation; foreign technicians can install equipment under B-1 but cannot perform construction; a parent's design office can do design but not seal drawings. A contractor that has done this before has the explanation ready. One that has not will learn on your project.
CTECP works in the United States through CTECP INC, with locations in Katy (Houston), Dallas and Greenville, South Carolina. The group has delivered 250+ industrial projects and 580,000+ m² across 9 countries since 2016, with design and supply-chain capacity in China and licensed local delivery teams.