Most contractor selection processes compare prices that are not comparable. The useful work is earlier: making the proposals describe the same scope, and verifying the things about a company that can be checked rather than claimed.
Start with what you can verify yourself
Mexico has an unusual advantage for buyers: several things a contractor claims are publicly or officially verifiable. Ask for them in writing and check them.
| RFC (tax ID) | Confirms the legal entity exists and is in the general corporate regime. A proposal from an entity whose name does not match the RFC is a problem worth resolving before anything else. |
| REPSE registration | Mandatory registration for companies providing specialised services or specialised works. For most industrial contracting this is not optional, and the registration has a number, an activity scope and an expiry. Ask for the current notice, not a screenshot of an old one — and check that the registered activity actually covers the work you are contracting. |
| IMSS standing | Social security compliance. In Mexican construction this is not an administrative detail: unresolved IMSS obligations become the client's problem at handover, through the SIROC process. |
| Insurance and bonding capacity | Ask for the certificate and the limits, not a statement that they are 'fully insured'. |
BOX:If a contractor cannot produce these within a day or two, that is itself the answer. Companies that hold them have them on file; companies that do not will explain why the question is unnecessary.
Make the proposals comparable before you compare prices
Two proposals for the same plant routinely differ by a large margin for one reason: they do not cover the same scope. The difference is almost never in the headline, it is in what is absent.
The items that most often come back later as variations:
- Ground improvement — what soil assumption was the price based on, and is that assumption written down?
- Utility connections — CFE electrical service and transformer, water, sewer, gas. These are administrative processes with their own calendars, and whoever owns them owns a schedule risk.
- Permit fees and the permitting work itself — municipal licence, land use, environmental where applicable, and occupancy.
- Fire protection — sized to what commodity class and what storage height?
- Process services — compressed air, process water, effluent, point extraction.
- Offsite works — access road, perimeter, parking, security.
- Commissioning, training and closeout documentation.
A practical method: send the same seven-item list to every bidder and ask each to state included or excluded for each. The proposals become comparable, and the quality of the answers is itself information.
What a reference check should establish
Asking "have you built a plant like this?" produces a yes from everyone. Three questions produce something useful:
| Under which legal entity? | Groups often hold work under different entities. The experience may be real and still not belong to the entity that will sign your contract — which matters if something goes wrong. |
| In what scope? | Installing equipment in someone else's building and delivering a turnkey facility produce the same photographs. Ask what the contract covered: civil only, installation only, or design through commissioning. |
| At what performance level? | For controlled environments, 'we have built cleanrooms' is not an answer. ISO 8 at-rest and sterile pharmaceutical Grade A/B are different undertakings with different qualification burdens. |
A contractor who answers these three precisely — including where the answer is unflattering — is giving you more information than one with a longer list.
Reading the contract structure
Beyond price, five clauses determine how the project will actually behave:
- Acceptance criteria. Which measurement, what value, who signs. If this is vague, handover is a negotiation.
- Closeout package contents. As-builts, material certificates, test protocols, balancing records, training. List it in the contract — at handover it becomes whatever is convenient.
- Change management. How a variation is priced, who approves it, and how its schedule effect is calculated. Projects are rarely damaged by the first variation; they are damaged by having no agreed method for the twentieth.
- Delay and force majeure. Specifically: where do permit and utility delays sit? These are the most common causes and the most commonly unassigned.
- Retention and warranty. Amount, release conditions, response time.
Signals worth weighting
| Raises problems before signature | A contractor who brings up a missing geotechnical report, an unclear commodity class or an authorisation question during the proposal stage is not being difficult. They are showing you how they will behave when something is genuinely unclear on site. |
| Writes down what they do not do | An explicit exclusions list and a statement of where their experience ends is a stronger signal than a capability list that covers everything. |
| Has its own site supervision | Ask whether site management is employed or subcontracted. Subcontracted supervision is not disqualifying, but it changes who is accountable day to day and you should know which it is. |
| Programme shows the non-construction items | A programme with separate lines for the CFE connection, permits and long-lead equipment has been thought about. One that starts at mobilisation has not. |
Where design-build and EPC change the calculus
Under a traditional split, the gap between the designer's documents and the builder's scope is the client's risk. Under design-build or EPC it moves to the contractor — which is the main thing you are buying.
Two consequences for selection:
- Your specification matters more, not less. A fixed price implies a fixed scope; a fixed-price contract over an underdefined scope is a deferred dispute.
- You are buying judgement as much as capacity. Under traditional contracting you can correct a weak contractor with a strong designer. Under EPC, both roles are inside the same company.
This is also why a technically competent reviewer on the owner's side remains worth having under EPC — not to duplicate the contractor, but to read the specification the way a builder will read it before it is attached to a contract.
How we answer these questions
We publish our own verifiable identifiers and state scope limits in writing because the questions above are the ones we would ask.
- Mexican entity CTECP, S.A. de C.V., with current REPSE registration covering construction of buildings, housing, infrastructure and civil works.
- Proposals carry an explicit scope list and an exclusions list, with acceptance criteria and the contents of the closeout package attached.
- Site management is our own, not subcontracted.
- Where our experience ends we say so: we have no track record in sterile pharmaceutical manufacturing (Grade A/B) and do not present ourselves as a turnkey contractor in that space; controlled environments we deliver to ISO 8 at-rest. We are not the responsible party for qualification and process validation.