A steel design can be fully compliant and still be the wrong design — because the sections it calls for are not what a Mexican mill or stockist actually sells. That gap is discovered at the cutting list, long after the drawings were approved.
Compliant is not the same as locally buildable
This is the single most common problem when a structure is engineered in one country and built in another. Three forms of it, all expensive, all found at the same moment — when someone produces the cutting list:
| Members longer than stock length | Structural sections are rolled and sold in standard lengths. A member designed longer than what the mill stocks has to be spliced — which adds a connection, an inspection point and a weld that was never in the design — or special-ordered, which adds lead time. Neither was in the price. |
| Sections that have no local equivalent | Section catalogues differ. A profile that is standard in a Chinese or European catalogue may have no counterpart in what Mexican stockists carry. The substitution is then made under schedule pressure, by whoever is fastest, and a 'closest available' substitution is a structural decision being made by procurement. |
| Plate thickness in the wrong unit system | Plate in this market is commonly produced on imperial increments even when it is quoted in millimetres. A design calling for 10 mm plate is quietly supplied as ⅜ in — about 9.5 mm. That is thinner, not thicker, and nobody flags it, because the purchase order says 10 mm. |
BOX:The check that prevents all three: run the cutting list against what is actually available locally before the design is frozen, not after it is approved. It is a few days of work at the design stage and a redesign after it.
Who designs the connections
This is the most common contractual gap in steel, and it is worth settling in writing before anyone quotes.
The structural engineer sizes the members. But the connections — plates, bolts, welds, stiffeners — may be designed by the engineer of record, or delegated to the fabricator against forces the engineer specifies. Both are legitimate. What is not legitimate is leaving it unstated, because then the fabricator prices it as excluded and the engineer assumes it is included.
- If connections are delegated, the design drawings must state the forces at each connection — not just member sizes. A fabricator cannot design a connection against an unstated force.
- Someone must review and accept the delegated design, and that review has to be in the programme. It is routinely forgotten and routinely on the critical path.
- Seismic detailing changes this conversation. Where ductile behaviour is required, the connection is not a detail that can be left to the shop — the ductility is in the connection, and it has to be engineered as such.
Anchor bolts: the first thing that goes wrong
Anchor bolts are cast into concrete weeks before the steel arrives, usually by a different crew than the one that will erect on them. Every error made here is found by a crane on hourly rate.
- Use a template, not a measurement. Bolts positioned individually to a dimension drift; bolts set in a fabricated template do not.
- Agree the tolerance in advance, and make sure the base plate holes are detailed to accept it. A tolerance the base plate cannot absorb is not a tolerance.
- Protect the threads. A bolt that survived the pour but not the subsequent slab work costs the same as one set in the wrong place.
- Survey before steel ships, not on the day it arrives. If something has to be corrected, it is far cheaper to know while the trucks are still loading.
Constraints that should shape the design, not surprise it
| Galvanizing kettle size | If members are to be hot-dip galvanized, the kettle sets the maximum piece length. A member longer than the available kettle has to be double-dipped or spliced. Confirm the kettle dimensions before fixing member lengths — this is a physical constraint on the design that is almost never checked at design stage. |
| Transport envelope | Road limits on length, width and height determine what can be shop-assembled and what must be bolted on site. A design optimised for shop assembly that cannot be transported is not optimised. |
| Crane access and erection sequence | What can be lifted, from where, and in what order is a design input on congested or brownfield sites. It is the reason an erection plan belongs in the design review and not in the method statement. |
| Fire protection | Whether members are intumescent-coated, boxed or left exposed changes section selection and the surface preparation specification — and it is frequently driven by the insurer rather than by code. |
Fabrication quality: what a document actually proves
«Certified welders» and «inspected welds» are claims. The question is what evidence exists.
- Qualified welding procedures for the material and joint types actually used, not a generic procedure on file
- Welder qualification records matched to the welders on the job, current at the time of the work
- An NDT scope defined in advance — which joints, what method, what acceptance criteria, and what happens on a rejection
- Material traceability — mill certificates matched to heat numbers, which is also what an insurer or an auditor asks for later
- Dimensional control in the shop, because a member that is out of tolerance is found either in the shop or by a crane
⚠️ Imported steel adds a layer: the certificates have to satisfy both the specification and customs. A shipment that is technically correct and documentarily incomplete sits at the border, and that delay lands on the erection window.
Local, imported, or both
| Where it helps | What it costs | |
|---|---|---|
| Local fabrication | Shorter lead time, no customs exposure, revisions are a phone call | Capacity varies; the catalogue constrains the design |
| Imported fabrication | Access to sections and capacity not available locally; can suit a design already engineered abroad | Lead time, freight, customs documentation, and revisions become expensive |
| Mixed | Main frame imported, secondary steel and miscellaneous local — common and usually sensible | The interface between the two scopes has to be drawn and assigned, or it becomes the gap |
There is no general answer; it depends on the sections the design needs and the schedule. What there is, is a general error: deciding this after the design is frozen, when the decision should have informed the design.
How we work
We fabricate and erect steel as part of the same contract as the civil works and the building services, and we model the structure together with MEP and envelope — so the interferences surface as desk observations rather than as rework on erected steel.
Where a structure has been engineered abroad, the first thing we do is run the cutting list against what is actually procurable here and come back with the list of members that need substitution, splicing or import — before the design is frozen, while changing it is still cheap.
The boundary: where we are not the engineer of record, we do not take responsibility for member sizing. We take responsibility for fabrication, erection, the delegated connection design where that is our scope, and for telling you which parts of the design will not survive contact with local procurement.
