Leasing a shell is fast; making it a working facility is a construction project with a landlord in it. Most fit-out disputes come from one unexamined assumption — that something is 'in the building' when the lease never said so.

What a shell usually is — and what it usually is not

Industrial shells in Mexican parks vary, but the common baseline is: structure, roof, walls, slab, basic lighting, a fire protection system sized for a generic commodity class, a service entrance, and often a small office block.

What is typically not there, and becomes fit-out scope:

BOX:The single most common surprise is electrical capacity. The shell's service entrance was sized for a generic tenant. If your process needs more, the gap is yours and it runs on CFE's calendar, not the landlord's.

Reading the TI allowance correctly

A tenant improvement allowance is a contribution, not a scope. Three questions decide what it is actually worth:

What does it coverHard construction only, or also design, permits and management? An allowance that excludes soft costs is materially smaller than the headline figure.
How is it paidAgainst progress, or on completion? Reimbursement on completion means you finance the whole fit-out and recover it later — a working capital question, not a cost question.
Who owns the resultImprovements usually become the landlord's property at lease end. That is normal, but it affects whether you should spend the allowance on things you can remove or things you cannot.
What happens if you spend lessSome leases let the balance offset rent; many simply let it lapse.

⚠️ Approval mechanics matter as much as the number: who approves the drawings, within how many days, and what happens to the schedule while you wait. An allowance with an open-ended landlord approval step is a schedule risk with a number attached.

Where the scope line sits

The practical split to write down before signing:

ItemUsually landlordUsually tenant
Structure, roof, envelope, slab✔
Base fire protection✔Upgrade if commodity class changes
Service entrance / base electrical capacity✔Distribution and any capacity increase
Office build-outSometimes a base amountAnything beyond it
Process HVAC, compressed air, process water✔
Equipment foundations and anchorage✔
Racking and mezzanines✔
Restoration at lease end✔ (per lease)

This table is a starting point, not a rule. Every lease moves at least two of these lines. What matters is that each one is assigned in writing before the lease is signed — afterwards you are negotiating from a weaker position.

Permits: work inside a leased building is still permitted work

A fit-out is not exempt from municipal process simply because the shell already has an occupancy permit. Points that commonly catch tenants:

Schedule: the fit-out is rarely the long pole

What actually sets the date:

A fit-out programme that does not show these four as separate lines is a construction programme, not a project programme.

Restoration at the end — decided at the beginning

Most industrial leases require the tenant to restore the premises, with the landlord able to require removal of some or all improvements. The cost of that obligation is created on the day you design the fit-out, and it is nearly always ignored then.

Two practical moves: agree in writing at lease signature which elements may remain, and keep an as-built record of what was installed and when — reconstructing it years later, from a different team, is where restoration disputes come from.

How we work on fit-outs

We take fit-out and tenant improvement work under a single contract: design, permits support, construction, MEP and process services, with as-built documentation and material certificates in the closeout package.

Because fit-out runs inside someone else's building, we treat two things as deliverables in their own right: a written scope split against the lease, and a programme that shows utility capacity and long-lead equipment as separate lines — those are what the schedule actually turns on.

Leased a building in Mexico? We’ll make it ready to operate.

Get a Quote →
More insights
Industrial Parks in Mexico: How to Choose → Adecuación de naves y tenant improvement (ES) →

Frequently asked questions

What is usually not included in an industrial shell?

Typically: power distribution beyond the service entrance, HVAC beyond the office, process ventilation, compressed air and process water, office build-out to your real headcount, data and security, racking and mezzanines, equipment foundations and anchorage, controlled environments, and fire protection upgrades if your commodity class differs from the base design. The most common surprise is electrical capacity — the service entrance was sized for a generic tenant, and increasing it runs on CFE's calendar.

How should I evaluate a tenant improvement allowance?

Four questions: does it cover soft costs (design, permits, management) or only hard construction; is it paid against progress or reimbursed on completion (which means you finance the work); who owns the improvements at lease end; and does an unspent balance offset rent or lapse. Also check the approval mechanics — an allowance with an open-ended landlord approval step is a schedule risk with a number attached.

Do I need a permit for work inside a leased building?

Generally yes. A fit-out is not exempt from municipal process because the shell already has an occupancy permit, and the landlord's consent is usually a prerequisite for filing. New partitions, mezzanines and racking change compartmentation, egress and smoke management, which triggers fire authority review. Mezzanines are frequently treated as new floor area, affecting both permits and the measured area under the lease.

What usually sets the fit-out schedule?

Rarely the construction. Four items dominate: an electrical capacity increase (CFE's process), long-lead equipment such as switchgear, chillers, air handling units and compressors, landlord approval cycles, and permits. A programme that does not show these as separate lines is a construction programme, not a project programme.

Who pays to restore the premises at the end of the lease?

Normally the tenant, with the landlord able to require removal of some or all improvements. The cost of that obligation is created when the fit-out is designed and is almost always ignored at that point. Agree in writing at lease signature which elements may remain, and keep an as-built record of what was installed — restoration disputes usually come from nobody being able to reconstruct that years later.