Leasing a shell is fast; making it a working facility is a construction project with a landlord in it. Most fit-out disputes come from one unexamined assumption — that something is 'in the building' when the lease never said so.
What a shell usually is — and what it usually is not
Industrial shells in Mexican parks vary, but the common baseline is: structure, roof, walls, slab, basic lighting, a fire protection system sized for a generic commodity class, a service entrance, and often a small office block.
What is typically not there, and becomes fit-out scope:
- Power distribution beyond the service entrance — panels, feeders, transformer if the demand exceeds what was provided
- HVAC for anything beyond the office, and any process ventilation or extraction
- Compressed air, process water, drainage for process effluent
- Office and amenity build-out to the headcount actually planned
- Data and security infrastructure
- Racking, mezzanines, equipment foundations and anchorage
- Controlled environments (clean areas, temperature or humidity control)
- Fire protection upgrades if your commodity class differs from the base design
BOX:The single most common surprise is electrical capacity. The shell's service entrance was sized for a generic tenant. If your process needs more, the gap is yours and it runs on CFE's calendar, not the landlord's.
Reading the TI allowance correctly
A tenant improvement allowance is a contribution, not a scope. Three questions decide what it is actually worth:
| What does it cover | Hard construction only, or also design, permits and management? An allowance that excludes soft costs is materially smaller than the headline figure. |
| How is it paid | Against progress, or on completion? Reimbursement on completion means you finance the whole fit-out and recover it later — a working capital question, not a cost question. |
| Who owns the result | Improvements usually become the landlord's property at lease end. That is normal, but it affects whether you should spend the allowance on things you can remove or things you cannot. |
| What happens if you spend less | Some leases let the balance offset rent; many simply let it lapse. |
⚠️ Approval mechanics matter as much as the number: who approves the drawings, within how many days, and what happens to the schedule while you wait. An allowance with an open-ended landlord approval step is a schedule risk with a number attached.
Where the scope line sits
The practical split to write down before signing:
| Item | Usually landlord | Usually tenant |
|---|---|---|
| Structure, roof, envelope, slab | ✔ | |
| Base fire protection | ✔ | Upgrade if commodity class changes |
| Service entrance / base electrical capacity | ✔ | Distribution and any capacity increase |
| Office build-out | Sometimes a base amount | Anything beyond it |
| Process HVAC, compressed air, process water | ✔ | |
| Equipment foundations and anchorage | ✔ | |
| Racking and mezzanines | ✔ | |
| Restoration at lease end | ✔ (per lease) |
This table is a starting point, not a rule. Every lease moves at least two of these lines. What matters is that each one is assigned in writing before the lease is signed — afterwards you are negotiating from a weaker position.
Permits: work inside a leased building is still permitted work
A fit-out is not exempt from municipal process simply because the shell already has an occupancy permit. Points that commonly catch tenants:
- Who holds the permit. Works inside a leased building generally still require a municipal construction licence, and the landlord's consent is a prerequisite for filing it.
- Fire and life safety. New partitions, mezzanines and racking change compartmentation, egress paths and smoke management. Fire authority review is triggered by the change, not by the building's age.
- Operating permits. Your operation may need approvals the building already has or does not have — environmental, health, or sector-specific. These run on their own calendar.
- Mezzanines. Frequently treated as new floor area, with implications for both permits and the lease's measured area.
Schedule: the fit-out is rarely the long pole
What actually sets the date:
- Electrical capacity increase — if a transformer or a higher service is needed, CFE's process dominates everything else. File first, design around it second.
- Long-lead equipment — switchgear, chillers, air handling units, compressors. Order dates are set backwards from delivery times, not from the construction programme.
- Landlord approvals — each review cycle is calendar time you do not control.
- Permits — parallel, but sequenced.
A fit-out programme that does not show these four as separate lines is a construction programme, not a project programme.
Restoration at the end — decided at the beginning
Most industrial leases require the tenant to restore the premises, with the landlord able to require removal of some or all improvements. The cost of that obligation is created on the day you design the fit-out, and it is nearly always ignored then.
Two practical moves: agree in writing at lease signature which elements may remain, and keep an as-built record of what was installed and when — reconstructing it years later, from a different team, is where restoration disputes come from.
How we work on fit-outs
We take fit-out and tenant improvement work under a single contract: design, permits support, construction, MEP and process services, with as-built documentation and material certificates in the closeout package.
Because fit-out runs inside someone else's building, we treat two things as deliverables in their own right: a written scope split against the lease, and a programme that shows utility capacity and long-lead equipment as separate lines — those are what the schedule actually turns on.